- Owner:
- Sportium
- Place
- Assago, Assago Forum
- Works start:
- 20/09/2023
Description
The project for the new ice rink at the Assago Forum, which began in 2023, is expected to be completed by the end of 2024. The facility will host the Figure Skating and Short Track competitions for the 2026 Milan-Cortina Olympics.
Schedule
Construction of the new ice rink began in 2023, with completion and preparation for Figure Skating and Short Track competitions scheduled for the end of 2024.
- in progress
1 Ideation
Il progetto della nuova pista di ghiaccio al Forum di Assago, avviato nel 2023, prevede il completamento entro la fine del 2024. La struttura ospiterà le competizioni di Pattinaggio di Figura e Short Track per le Olimpiadi Milano-Cortina 2026.
2 Design
La fase di progettazione ha visto la definizione degli impianti, con particolare attenzione alla sicurezza, all'efficienza energetica e alle specifiche tecniche per le competizioni olimpiche di Milano-Cortina 2026.
3 Execution of the work
L'esecuzione dei lavori ha comportato la costruzione della pista di ghiaccio, l'installazione di impianti tecnologici avanzati e la realizzazione di strutture per ospitare competizioni e allenamenti olimpici.
4 End of work
La fase di fine lavori ha visto la conclusione delle strutture, il collaudo degli impianti e la preparazione finale per le competizioni olimpiche, con la consegna delle opere completate entro la fine del 2024.
Gallery
History
The Assago Forum, now known as the Unipol Forum, opened in 1990. With a volume of 450,000 cubic metres, a covered area of 40,000 square metres and a central arena spread over three levels with a total capacity of 15,800 spectators, it is one of Europe’s leading multi-purpose venues.
This particularly innovative facility won the European Architecture Award for sports facilities in 1994, awarded by CONI and the Council of Europe.
The refurbishment of the Unipol Forum in Assago ahead of the XXV Milan-Cortina 2026 Winter Olympic Games involves the installation of a new high-performance ice rink for figure skating and short track competitions.
The project combines technological innovation, precision in execution and construction quality to meet the rigour of Olympic standards: the project involves the installation of a jointless concrete floor, capable of ensuring flatness, surface continuity, mechanical strength and durability, whilst reducing the risk of cracking.
Constructed in a single phase to ensure uniformity and reduced construction times, the project covered a total area of 1,800 square metres.