- Owner:
- Vitali spa
- Works start:
- 16/03/2024
Description
The redevelopment of the former Service Centre is part of the Porta Sud project, which involves demolishing obsolete structures and preparing the area for new urban developments. The project will revitalise a strategic area in the south of Bergamo.
Schedule
The project involves the initial demolition of the former Service Centre, the reclamation and securing of the area, followed by the preparation of the land and urbanisation works that anticipate future interventions in Porta Sud.
- in progress
1 Ideation
La fase di ideazione ha previsto l’analisi dell’area ex Centro Servizi e la definizione degli obiettivi di riqualificazione, orientando il progetto verso una trasformazione urbana moderna e sostenibile.
2 Design
La progettazione ha definito modalità, fasi e obiettivi della riqualificazione dell’ex Centro Servizi, integrando sicurezza, sostenibilità e nuove funzioni per valorizzare l’area Porta Sud.
3 Execution of the work
Durante l’esecuzione lavori sono state demolite le strutture esistenti, svolte le bonifiche necessarie e predisposta l’area per le future opere di Porta Sud, garantendo sicurezza e continuità operativa.
4 End of work
A fine lavori l’area dell’ex Centro Servizi è stata completamente liberata, bonificata e messa in sicurezza, risultando pronta per le successive opere di trasformazione previste dal progetto Porta Sud.
Gallery
History
Commencing in February 2024, the demolition of the former Bergamo Service Centre marks the end of a building that has stood unfinished for 28 years, having cost 100 billion lire and originally intended to serve as the Ministry of Finance’s archive for paper tax documents, before being abandoned as the digitisation of records progressed. Thanks to the purchase by Vitali S.p.A. and the commitment of Bergamo City Council and local authorities, the site is set to undergo a radical transformation. The ‘strip-out’ operations, involving the selective demolition of non-structural components, are now underway.
The former Service Centre, originally an ambitious project covering an area of 20,000 square metres, forms part of the wider area of the new urban regeneration project, which also includes the northern sectors acquired by A2A, totalling almost 130,000 square metres. The figures highlight the scale, complexity and value of the project for the city of Bergamo and the neighbouring municipalities of Azzano San Paolo and Orio al Serio.
The area will host new facilities serving both private and public interests: on the northern plots, A2A will consolidate the three sites currently located within the city. Vitali S.p.A. is working to build a centre of approximately 9,000 square metres in the southern area, to manage the process of transferring goods to their final destination. There will also be parking spaces and a 7,000-square-metre site dedicated to the manufacturing sector. The city’s second recycling centre will also be built.
In addition to the construction of all internal roadworks within the development, the project also includes further improvements to the road network, such as the construction of two new roundabouts: one in the Municipality of Bergamo, at the junction of Via Zanica, Via Campagnola and Via De Saussure; the other in the municipality of Azzano, along the Cremasca municipal road, with associated ancillary works to facilitate use of the roundabout, such as the upgrading of the bridge over the Morla stream; finally, works are planned in the municipality of Orio al Serio to convert Via Portico into a one-way street.