Waste to energy plant demolition

Waste to energy plant demolition

Owner:
Vitali spa
Works start:
30/06/2021

Description

The project involved the deconstruction of the old waste-to-energy plant in Bolzano. The work, worth approximately €3 million, included the removal of the plant, the demolition of the structures and the securing of the area.

Schedule

The dismantling, remediation and demolition work began in July 2021 and was entrusted to a temporary consortium with an expected duration of eight months. Despite previous delays, the construction site operated without interfering with the adjacent plant.

  1. in progress

From to

Gallery

History

The waste-to-energy plant, located on the left bank of the River Isarco in the industrial area to the south-east of the city, was decommissioned in 2013 and subsequently made safe in 2015: It consists of two incineration lines, the first commissioned in 1988 and the second in 1996, both comprising a flue gas treatment section and a technical cycle for energy production.

The project involves the dismantling and decontamination of the plant systems comprising the two incineration lines of the old waste-to-energy plant, the demolition of the structures and earthworks, including the construction of stormwater drains, the relocation of a medium-pressure gas pipeline and surface waterproofing. The works are being carried out without disrupting the new plant, adjacent to the site, so as to ensure its continuous operation, maintain traffic flow along the Brenner Motorway and Via Lungo Isarco Sinistro, and provide access for staff to the Seab warehouses.

During the works, particular attention is being paid to the correct disposal of potentially polluting components: dust, residual ash produced by the thermal cycle, insulation materials containing mineral fibres, pipes, tanks, and refractory components and materials present in the chimney and in the combustion and post-combustion chambers. The actual demolition will commence once the dismantling and decontamination of all plant components have been carried out in a controlled environment.

To separate the waste produced at source and send it for recovery, specific equipment is used for the demolition of refractory materials inside the chimney: mounted on a crane arm, the device is lowered into the chimney and progressively demolishes the refractory materials, causing them to fall to the ground so that they can then be recovered and disposed of. Once the interior has been demolished, the exterior of the chimney will be demolished using a specialised demolition vehicle, radio-controlled and radio-guided, equipped with an arm over 50 metres long.

Given the specific nature of the steel structures to be demolished, a 70-tonne vehicle specially designed for the operation will be deployed, capable of operating a 7.5-tonne hydraulic shear at a height of 18 metres and another 3.5-tonne hydraulic grapple that will operate at a height of over 30 metres.

1776 views