Lorini construction site

Lorini construction site

Owner:
Vitali spa
Works start:
20/09/2024

Description

The demolition of the Lorini office building is proceeding with the removal of the superstructure and metal debris. The site is being prepared for clearance and levelling, with a view to recovering materials and adapting the area.

Schedule

Work commenced on 20 September 2024 and will continue until 21 February 2025. The current phases include removal of the structure, clearing of rubble and levelling, with completion in February 2025.

  1. in progress

From to